Report: Oversight lacking in NYC payroll project

July 25, 2014 Associated Press
Bloomberg in 2011. AP photo
Share this:

Investigators say poor oversight allowed a New York City payroll-technology project to spiral into a $700 million tangle of contractor fraud, budget overruns and delays.

A Department of Investigation report released Friday says the city lacked proper management safeguards to detect and prevent the problems with the CityTime project.

Its costs ballooned from about $70 million to $700 million. Authorities later concluded a key contractor hired and overpaid consultants through companies his associates owned.

Subscribe to our newsletters

Eight people have been convicted or pleaded guilty. The prime company on the project repaid the city more than $500 million.

The Department of Investigation recommends assigning an “integrity monitor” to all major technology projects. It also wants to require consultants on such projects to undergo conflict-of-interest background checks.

The mayor’s office had no immediate comment.